BC Hydro - Structural Towers for Saltary Bay and Malaspina


BC Hydro – Structural Towers for Saltary Bay and Malaspina Job # 1288-1293 Weight 460,000 lbs Unifab was awarded a project to design, fabricate, galvanize, and deliver the towers and equipment support scope required for BC Hydro (BCTC) to implement major upgrades to two of their electric substations on the Sunshine Coast of British Columbia. 1293-Malaspina-Termination-TowersWorking with BCTC’s, EPCM partner, SNC Lavalin, Unifab developed the design, and expedited fabrication and supply against a tight schedule.  Requiring test assembly and barge shipping to two remote coastal ports, Unifab met schedule and delivered 93 distinct structures of steel.